Case Highlights
The 37-mile transport route for this 370,000-lb transformer presented multiple challenges, including more than 200 overhead wires, multiple narrow streets, and tight corners. Buckingham’s detailed route planning, swept path analysis, and on-the-ground expertise enabled us to safely complete the delivery while minimizing disruptions to traffic flow and surrounding infrastructure.
Client Satisfaction
Despite delays caused by Hurricane Helene, Buckingham maintained strong communication with all stakeholders, coordinating details and enabling the project to proceed smoothly when conditions allowed.
Equipment Used
- 10 Lines Goldhofer Dual Lane Trailer
- Buckingham Jack & Slide System
- Kenworth W990